The phase definitions link has been added to the Project/Activity detail,
modify, and add pages.
Kris
At 8:34 PM -0500 11/27/2000, Robert Ferrara wrote:
>Like 'em all.
>
>Cheers, Bob
>
>At 02:43 PM 11/27/2000 -0500, Tim McGovern wrote:
>>Try these for a start:
>>
>>> Planned
>> Preliminary work is underway to define, scope and resource
>>
>>> Project
>> Work to investigate or implement defined deliverables is underway
>>
>>> Operational
>> Product or service now deployed to the community
>>
>>> In Service
>> Product or service operational, and full production quality
>>
>>> Finished
>> Work halted prior to operational deployment with no outstanding issues
>>
>>> Cancelled
>> Work halted prior to operational deployment due to major issues
>>
>>Comments, everyone?
>>