Project Name: Enterprise Backup System
Project Leader: Sebastien Sabre
Report Date: 12/12/02
URL: http://windsurf.mit.edu/ebs
Accomplishments Past Period:
----------------------------
* Continued daily maintenance and operation of NetBackup on the E40 systems.
* E40 backups success was 100% for November.
* Completed W91 rollout WBS.
* Met with our Sponsor.
* Started W91 implementation
- Started HW installation of the W91 master server
* Started knowledge transfer to new ASST resource (Dan Logcher)
Goals for the Coming Periods:
-----------------------------
* W91 implementation
- Complete HW installation of the W91 master server
- Install OS on W91 master server
- Install Nebackup software on master an media servers.
* Schedule ITAG review.
* Get final buy-in from key stakeholders (ASST, R3-Admin, DOST) on the E40
implementation.
- Schedule meeting
* Complete documentation
* Update project documentation and web pages.