Project Name:    Enterprise Backup System
Project Leader:  Sebastien Sabre
Report Date:     12/12/02
URL:             http://windsurf.mit.edu/ebs




Accomplishments Past Period:
----------------------------

* Continued daily maintenance and operation of NetBackup on the E40 systems.

* E40 backups success was 100% for November.

* Completed W91 rollout WBS.

* Met with our Sponsor.

* Started W91 implementation
   - Started HW installation of the W91 master server

* Started knowledge transfer to new ASST resource (Dan Logcher)



Goals for the Coming Periods:
-----------------------------

* W91 implementation
   - Complete HW installation of the W91 master server
   - Install OS on W91 master server
   - Install Nebackup software on master an media servers.

* Schedule ITAG review.

* Get final buy-in from key stakeholders (ASST, R3-Admin, DOST) on the E40 
implementation.
   - Schedule meeting

* Complete documentation

* Update project documentation and web pages.