Project Name: ECAT - New Vendors
Submitted by: Lorraine Rappaport
Report Date: October 7, 2002
Project URL: http://web.mit.edu/is/delivery/ecat
Accomplishments Past Period:
Dell:
- Rolled out Dell ECAT catalog to the community
Grainger:
- Completed testing and QA
- Moved configurations to production and began testing
PSB:
- Planned for meeting with Kathryn Willmore to discuss recommendation and
(hopefully) obtain approval for desired vendor partner
Herman Miller:
- They are just about ready to start integration work with us.
Goals for Next Period:
Grainger:
- Begin pilot
PSB:
- Meet with Kathryn Willmore and (hopefully) get approval to proceed.
Herman Miller:
- Discuss work plan and schedule
Next Community Milestone:
- Grainger pilot