Monthly Delivery Report for ECAT - New Vendors

daemon@ATHENA.MIT.EDU (Lorraine J. Rappaport)
Wed Sep 11 08:37:47 2002

Message-Id: <5.0.2.1.2.20020911082026.00aafda8@hesiod>
Date: Wed, 11 Sep 2002 08:36:00 -0400
To: delivery@mit.edu
From: "Lorraine J. Rappaport" <ljr@MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"; format=flowed

Project Name: ECAT - New Vendors
Submitted by: Lorraine Rappaport
Report Date: September 10, 2002
Project URL: http://web.mit.edu/is/delivery/ecat

Accomplishments Past Period:

Dell:
- Monitored production pilot activity
- Coordinated plans for full roll-out
- Drafted documentation for full roll-out

Grainger:
- Grainger completed modifications to their catalog and order 
request.  Once fully tested, they moved this code to their QA environment.
- FSS modified configuration of vendor number, which resolved the problem 
we encountered when trying to create WB reqs in SAP
- Created XML stylesheet for purchase order, tested, and sent samples to 
Grainger for review.

PSB:
- Continued efforts toward obtaining final approval for vendor recommendation
- Worked with desired vendor (can't really publicly divulge who yet) to 
build catalog
- Notified other vendors of status

Goals for Next Period:

Dell:
- Announce availability to community

Grainger:
- Complete testing of orders.
- Move to production for pilot

PSB:
- Obtain final approval for vendor selection
- Continue to work with vendor to build and integrate the catalog

Issues:

-None

Next Community Milestones:
- Roll out Dell community-wide
- Begin Grainger pilot