Project Name: Athena User Interface Project
Project Leader: Andrew Boardman
Report Date: 8 March 2002
Project URL: http://web.mit.edu/aui/notebook/
Accomplishments Past Period:
- Continued comparative/retrospective usability testing.
Goals for Next Period:
- Finish up the paperwork and offically conclude the project; pass on
conclusions to the Athena Development teams as ideas for future work.
Issues:
- We haven't had too many subjects for usability testing, but the tests
we've done have had consistent (and positive) results, so we should be
finishing up this month, one way or the other.
Team Dynamics:
- Fine.