Note from 10/28 meeting (Barbara, Debi, Wade)

-  Updated project plan (see below)

-  Noted that final date for development is end of day Monday
   November 10, 1997.

-  Cut-over from Filemaker to Oracle to begin after 5:00 pm on
   Friday, November 14, 1997.  Probably completed over the weekend and
   production available on Monday morning November 17, 1997.

-  Web/Oracle application is in good shape.  May be some missing fields
   that need to be added.  Development priority will shift to completing
   the email/oracle application with possible "live" testing before the
   November rollout date.

-  Discussion on possible items for phase 2.  There was consensus that
   greater support for consulting functions will be included.

-  David Ho and Peter Ragone will begin work on the Scopus GUI changes,
   making the six identified changes (see below) on the test
   database.  Weekly (Friday afternoon) status reports will be sent
   out to show progress.  David will also help coordinate the
   completion of the Scopus Windows NT installer.

-  Consultant accounts seem to be in good shape.  Debi and wade will
   re-load the Filemaker data by 10/30 with data fixes.

---------------------------------------------------------------------

The critical path items to manage are:

-  Set final date for development changes (NOTE: timeline leaves little time
   for development, therefore, need to identify showstoppers versus items
   that can be changed for a future release)

-  Testing, testing, testing:  Specifically the Scopus GUI and with
   regards to the Filemaker legacy data import.  Goal is to ensure
   continuity of business.

-  Identification of resources to ensure transition to Service and
   committment of Delivery resources to ensure a phase 2 release.

---------------------------------------------------------------------

HELP TOOLS RELEASE 1.1 WORKPLAN

TOOLS

Web/Oracle

      Complete application as follows:

      First priority is:
      -  Need further check on consulting access, don't allow legacy people to
         gain access (as currently is the case).  New view should resolve.
      -  Ensure https is restarted on reboot
      -  Change

      Rest of proposed changes:
      -  "modified by" username needs to be filled in via the web
      -  Submit record should have "client" as received by attribute.
      -  Change search "within 60 days" to between "30 and 60". ??
      -  Add "MIT Computing Help Desk" with appropriate mail address to the
         consultant reply to customer mail function.
      -  Change result screen working "Only first 100 records will be shown".
         to "Showing first xx matching entries".
      -  Main screen:  Change "Client:" to "Client Last Name:".
      -  Sorting on log status, sort in descending order by MIT_WEIGHT
      -  Change default sort order by (descending) log status weight and
         then log number on the "Staff" side?
      -  Revise format of the email sent to the customer.
      -  Change "Notify customer via email" to "Send customer new entry via
         email" or "Send customer new case history" depending what happens.
      -  Make this checkbox only appear if we know the customer's email
         address?
      -  Search on other stati, including "taker" field

      Testing, specifically, Web and Scopus interaction
      Status:     Open
      Assigned:   Ragone
      Target:     10/29  (may slip, Scopus GUI changes higher priority)

      Testing, specifically, previously completed items
      Status:     Open
      Assigned:   Fuchs
      Target:     10/27


Scopus GUI:

      Complete GUI changes as follows (priority is shown):
      1. Add new Find Open scripts per category (see debi's mail)
      2. Add Next Step field
      3. Modify Find Open script to handle frozen date (do not show
         Frozen logs in result window with a date greater than today.
      4. Bug fix: on required field error, status reverts to New
      5. Bug check: switching between main log and network screen, old
         data shows on network screen when selecting new main log.
      6. Change label from "Thaw" to "Close on Thaw"

      Status:     Working
      Assigned:   Ho/Ragone
      Target:     10/31

      Testing, specifically gap analysis between Filemaker and Scopus
      Status:     Open
      Assigned:   Ragone (time is issue, may not be completed)
      Target:     10/27

Email/Oracle

   Review, complete and migrate to production:
   -  Minor changes include not hardcoding the login password
      acknowledgement message.
   -  Install on production machine, revise syslog
   -  Need acknowldegement message on "reply logid"
   -  Need customized acknowldegement message on new message
   -  Needs testing
   -  Review history to not have fixed upper limit
   -  Add code to handle bounced mail

      Status:     Open
      Assigned:   Wade
      Target:     11/07

SYSTEM:

Database

      Add missing database fields:
	Next Step field.
      Status:     Completed
      Assigned:   Wade
      Target:     10/21

      Create cron process to modify Frozen logs based on Frozen date
      and status of Thaw code:
      Status:     Open
      Assigned:   Wade
      Target:     11/07

      Create new view "legacy_users" to not display legacy users.
      Status:     Open
      Assigned:   Wade
      Target:     10/30

      Export test help-them database to production help-it database
      Status:     First attempt completed
      Assigned:   Wade
      Target:     10/22

Data updates:

      Update lookup/code tables as follows:
        Add "Web" to Method, add "Unseen" to Status,
        remove "Referred" from status, add "Projects" and "CWIS"
        to Category, remove "Waiting" from status.

	Status:   Completed 10/20

Account table maintenance:

      Review, modify and create new accounts:
        Add "client" to profile and users table.
        Drop those accounts where people do not need to login.
        Move old consultants to status of Legacy
        Add new users
        Add Legacy users

      Status:     Completed 10/20

      Alter the password for existing accounts
      Status:     Open
      Assigned:   Debi
      Target:     10/27

Overall testing:

      Perform business, stress and data testing
      Status:     Open
      Assigned:   Computing Help Desk
      Target:     10/22

ROLLOUT:

Filemaker/Oracle Conversion:

      Complete first pass and load of data

      Status:     Completed 10/21

      Complete second pass and load of data
      Need upper case for complete second pass and load of data

      Status:     Open
      Assigned:   Debi/Wade
      Target:     10/30

      Complete FINAL load of data

      Status:     Open
      Assigned:   Debi/Wade
      Target:     11/14

Scopus deployment:

      Install Scopus NT on machines as needed:
      Status:     Open
      Assigned:   Smyser/Ho
      Target:     10/22

Scopus Training:

      Ensure consultants are ready
      Status:     Open
      Assigned:   Allen/Smyser/Ragone/Fuchs
      Target:     Two training sessions planned, 10/31

Solicit appropriate feedback

      Check with DCS/Sampson for issues
      Status:     Open
      Assigned:   Fuchs/Goguen
      Target:     10/17

---------------------------------------------------------------------
HELP TOOLS RELEASE 1.2 ??

Solaris Scopus GUI needs to work with ANO
Web/Oracle - send consultant mail when customer updates log
Add private comments field
Review design to look at records that exceed limit on result query