Scopus Status Report 7/26/96

daemon@ATHENA.MIT.EDU (Steven Wade Neiterman)
Tue Jul 30 09:12:28 1996

Date: Tue, 30 Jul 1996 09:15:32 -0400
To: tooltime@MIT.EDU
From: wade@MIT.EDU (Steven Wade Neiterman)

Scopus Implementation
Date: July 26,1996


Working On Milestone:

-  Beta phase continues with multiple releases, testing, and assessment
   of work required to complete this phase.

-  Next release 1.0b4 will be on August 2nd, with possible completion of
   the beta phase on August 9th.

Accomplishments:

-  Continued work on release 1.0b4, as measured against task list.
   Emphasis on record locking, bug fixes and InformTEAM for automated
   escalation.
-  Continued preparing for new machine deployment, waiting for ETA
-  Began first discussion of migration/rollout issues - to be refined
-  Continued with Tcl documentation

Goals:

-  Continue work on release 1.0b4, with completion by August 2nd.
-  Prepare for production machine purchasing/delivery

Issues:

-  Outstanding Macintosh problems, waiting for Scopus reply