Scopus Status Report 6/28/96

daemon@ATHENA.MIT.EDU (Steven Wade Neiterman)
Mon Jul 1 17:27:42 1996

Date: Mon, 1 Jul 1996 17:30:02 -0400
To: tooltime@MIT.EDU
From: wade@MIT.EDU (Steven Wade Neiterman)

Scopus Implementation
Date: June 28,1996


Working On Milestone:

-  Beta phase continues with multiple releases, testing, and assessment
   of work required to complete this phase.

-  Release 1.0b3 testing to begin week of July 1.

-  Initial beta phase completion goal (June 30) has slipped.
   Now projected to be mid July for completion of a stable client of
   base/core functionality.

Accomplishments:

-  Completed (with the exception of 2 items for 7/1) release 1.0b3
-  Began introducing Scopus to assigned documentation resource
-  Called Scopus on Macintosh issues, no progress
-  Continued with student data/warehouse resolution

Goals:

-  Complete and release 1.0b3 for testing - 7/2
-  Obtain test results - 7/3
-  Meet with MIT Facilities Mgt on production machine 7/2
-  Organize meeting to discuss common needs of Help Desk/Software Listing
-  Continue with on-going tasks (see previous week's status report)

Issues:

-  Outstanding Macintosh problems, waiting for Scopus reply

Notes:

-  Possible impact as The Help Desk is moving on Monday 7/1.  Upcoming
   week is short (holiday 7/4-5), which may hinder time spent on
   testing if the 1.0b3 release is delayed.

-  If there are minimal changes to the 1.0b3 release, we should shift
   some of the implementation/testing resources towards updating system
   documentation and starting to evaluate rollout procedures.