Re: Suggestions for Mike's project-db homepage

daemon@ATHENA.MIT.EDU (Tim McGovern)
Tue Sep 2 16:44:13 1997

In-Reply-To: <199708182005.QAA18950@megara.MIT.EDU>
Date: Tue, 2 Sep 1997 16:43:11 -0400
To: Mike Barker <mbarker@MIT.EDU>
From: Tim McGovern <tjm@MIT.EDU>
Cc: project-db@MIT.EDU

>I think I did #12 (What is a Target Date?) after you looked at it.
>
>Comments?
>
>thanks
>Mike

I think your explanation is good enough for V2.  When we get
into details of V3, we might want to consider letting PMs, or task
assignees some control over what they mean by the date they're
providing.

Tim