Bldg. 8 - Rescheduled Building Power - 120/208 Volt Shutdown Requ
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Nov 13 13:42:30 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71CF9@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'carolr@mit.edu'" <carolr@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'ghughes@mit.edu'" <ghughes@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'lechtman@mit.edu'"
<lechtman@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: RM-ElecCtl <rm-elecctl@MIT.Edu>,
"'shutdown@plant.mit.edu'"
<shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>, C-Zone <C-Zone@MIT.Edu>
Date: Thu, 13 Nov 2003 13:36:41 -0500
> To: C-Zone; carolr@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; lechtman@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: RM-ElecCtl; shutdown@plant.mit.edu; rm-shutdown@mit.edu; C-Zone
> Subject: Bldg. 8 - Rescheduled Building Power - 120/208 Volt Shutdown
> Request
>
>
The following rescheduled 120/208V building power shutdown request for Bldg.
8 - 2nd floor only on Saturday, 11/15/03 is for your information and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 8 - 2nd floor
> Date: 11/20/2003
> Day: Thursday
> Time: 11 PM (11/20) - 7 AM (11/21)
> System: Building Power - 120V, 208V normal power
> Duration: 8 hours
> Reason:
> Activate new power panels for 2nd floor Van Vliet Lab renovation.
>
> Effect:
> Loss of 120V, 208V normal power in Bldg. 8 - 2nd floor. This means that
> no computers, lighting or receptacles will be operational during the
> shutdown period.
>
>