Bldg. 14 - Air Handler 6 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Nov 6 12:47:30 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D71C76@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@mit.edu>, "'altenb@mit.edu'" <altenb@mit.edu>,
        "'bkdavis@mit.edu'" <bkdavis@mit.edu>,
        "'cpomieko@mit.edu'"
	 <cpomieko@mit.edu>,
        "'csnyder@mit.edu'" <csnyder@mit.edu>,
        Cust-Coach
	 <cust-coach@mit.edu>,
        "'ellertsn@mit.edu'" <ellertsn@mit.edu>,
        "'emmh@mit.edu'" <emmh@mit.edu>, "'graposa@MIT.EDU'" <graposa@mit.edu>,
        "'jhlyons@mit.edu'" <jhlyons@mit.edu>,
        "'jmullins@mit.edu'"
	 <jmullins@mit.edu>,
        "'nlowe@mit.edu'" <nlowe@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'sdl-adm-lib@mit.edu'"
	 <sdl-adm-lib@mit.edu>,
        "'slarkin@mit.edu'" <slarkin@mit.edu>,
        "'susanne@mit.edu'" <susanne@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 6 Nov 2003 12:46:35 -0500 

> To: 	A-Zone; altenb@mit.edu; bkdavis@mit.edu; cpomieko@mit.edu;
> csnyder@mit.edu; Cust-Coach; ellertsn@mit.edu; emmh@mit.edu;
> graposa@MIT.EDU; jhlyons@mit.edu; jmullins@mit.edu; nlowe@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; slarkin@mit.edu; susanne@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 14 - Air Handler 6 Shutdown Request
> 
> 
The following air handler 6 shutdown request for Bldg. 14 - First Floor -
North Wing on Wednesday, Novemer 12, 2003 is for your information and
comment.  Would you please let me know whether this does or does not meet
with  your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 14 - First Floor - North Wing
> Date: 11/12/2003
> Day: Wednesday
> Time: 7 AM - 9 AM
> System: Air Handler 5
> Duration: 2 hours
> Reason: 
> Control System Upgrade.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in the
> above-mentioned areas. Also the Operations Center in E19  will be unable
> to monitor this air handler as well the control air compressor during the
> 2-hour Control Systems Upgrade period.
> 
> 