[69554] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 14 - Air Handlers 1, 2 and 3 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Nov 6 12:44:18 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D71C75@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'altenb@mit.edu'" <altenb@MIT.Edu>,
        "'bkdavis@mit.edu'" <bkdavis@MIT.Edu>,
        "'cpomieko@mit.edu'"
	 <cpomieko@MIT.Edu>,
        "'csnyder@mit.edu'" <csnyder@MIT.Edu>,
        Cust-Coach
	 <cust-coach@MIT.Edu>,
        "'ellertsn@mit.edu'" <ellertsn@MIT.Edu>,
        "'emmh@mit.edu'" <emmh@MIT.Edu>, "'graposa@MIT.EDU'" <graposa@MIT.Edu>,
        "'jhlyons@mit.edu'" <jhlyons@MIT.Edu>,
        "'jmullins@mit.edu'"
	 <jmullins@MIT.Edu>,
        "'nlowe@mit.edu'" <nlowe@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'sdl-adm-lib@mit.edu'"
	 <sdl-adm-lib@MIT.Edu>,
        "'slarkin@mit.edu'" <slarkin@MIT.Edu>,
        "'susanne@mit.edu'" <susanne@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 6 Nov 2003 12:38:49 -0500 

> To: 	A-Zone; altenb@mit.edu; bkdavis@mit.edu; cpomieko@mit.edu;
> csnyder@mit.edu; Cust-Coach; ellertsn@mit.edu; emmh@mit.edu;
> graposa@MIT.EDU; jhlyons@mit.edu; jmullins@mit.edu; nlowe@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; slarkin@mit.edu; susanne@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 14 - Air Handlers 1, 2 and 3 Shutdown Request
> 
> 
The following air handlers 1, 2 and 3 shutdown request for Bldg. 14 - East
Wing - Floors Basement through 3rd floor and South Wing East on Tuesday,
November 11, 2003 is for your information and comment.  Would you please let
me know whether this does or does not meet with your approval.

Thanks very much.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 14 - East Wing - Floors  Basement through 3rd floor and South
> Wing East
> Date: 11/11/2003
> Day: Tuesday
> Time: 7 AM - 9 AM
> System: Air Handlers 1, 2 and 3
> Duration: 2 hours
> Reason: 
> Control System Upgrade.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in the
> above-listed areas. The Operations Center in Bldg. E19 will not be able to
> monitor this area for air handlers or chilled water system#1 although that
> will remain on during this 2-hour upgrading period.
> 
> 