Bldg. E52 - Rescheduled Supply Fans 1 through 5 Shutdown/Filter C

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 4 15:08:14 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D71C3D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'aed@mit.edu'" <aed@mit.edu>, "'alterra@mit.edu'" <alterra@mit.edu>,
        "'dori123@mit.edu'" <dori123@mit.edu>, E-Zone <E-Zone@mit.edu>,
        "'gwj@mit.edu'" <gwj@mit.edu>, "'lhill@mit.edu'" <lhill@mit.edu>,
        "'lmorales@mit.edu'" <lmorales@mit.edu>,
        "'mscoppa@mit.edu'"
	 <mscoppa@mit.edu>,
        "'pconeeny@MIT.EDU'" <pconeeny@mit.edu>,
        "'rberlin@mit.edu'" <rberlin@mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@mit.edu>,
        "'sdimond@mit.edu'" <sdimond@mit.edu>,
        "'wganger@mit.edu'" <wganger@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 4 Nov 2003 15:05:18 -0500 

> To: 	aed@mit.edu; alterra@mit.edu; dori123@mit.edu; E-Zone; gwj@mit.edu;
> lhill@mit.edu; lmorales@mit.edu; mscoppa@mit.edu; pconeeny@MIT.EDU;
> rberlin@mit.edu; schedule@mit.edu; sdimond@mit.edu; wganger@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E52 - Rescheduled Supply Fans 1 through 5
> Shutdown/Filter Change Request
> 
> 
The following rescheduled supply fans 1 through 5 shutdown/filter change
request for Bldg. E52 - initially scheduled for Monday, October 13, 2003 has
been rescheduled to Tuesday, November 11, 2003 (Veteran's Day).  Would you
please let me know whether this does or does not meet with your approval.

Thank you again for your time.

Andrea Nichols
Repair and Maintenance
8-7872

P.S.  This has been approved by the Faculty Club.

> Status: Normal
> Building: N52 - Faculty Club and rest of the building
> Date: 11/11/2003
> Day: Tuesday
> Time: 8 AM - 12 PM
> System: Supply Fans 1 through 5/Must all be shutdown together - PM#70090,
> 700025, 70026, 70027 and 70028
> Duration: 4 hours
> Reason: 
> Pre and bag filter changes.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in Bldg. E52
> during the 4-hour shutdown/filter change period.
> 
> 