[69503] in Hotline Meeting
Bldg. 14 - Air Handlers 4 and 5 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 4 13:59:01 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71C3A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'altenb@mit.edu'" <altenb@MIT.Edu>,
"'bkdavis@mit.edu'" <bkdavis@MIT.Edu>,
"'cpomieko@mit.edu'"
<cpomieko@MIT.Edu>,
"'csnyder@mit.edu'" <csnyder@MIT.Edu>,
Cust-Coach
<cust-coach@MIT.Edu>,
"'ellertsn@mit.edu'" <ellertsn@MIT.Edu>,
"'emmh@mit.edu'" <emmh@MIT.Edu>, "'graposa@MIT.EDU'" <graposa@MIT.Edu>,
"'jhlyons@mit.edu'" <jhlyons@MIT.Edu>,
"'jmullins@mit.edu'"
<jmullins@MIT.Edu>,
"'nlowe@mit.edu'" <nlowe@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@MIT.Edu>,
"'slarkin@mit.edu'" <slarkin@MIT.Edu>,
"'susanne@mit.edu'" <susanne@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 4 Nov 2003 13:58:50 -0500
> To: A-Zone; altenb@mit.edu; bkdavis@mit.edu; cpomieko@mit.edu;
> csnyder@mit.edu; Cust-Coach; ellertsn@mit.edu; emmh@mit.edu;
> graposa@MIT.EDU; jhlyons@mit.edu; jmullins@mit.edu; nlowe@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; slarkin@mit.edu; susanne@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 14 - Air Handlers 4 and 5 Shutdown Request
>
>
The following air handlers 4 and 5 shutdown request for Bldg. 14 West - 111
(Killian Hall) and South Wing East on Monday, November 10, 2003 is for your
information and comment. Would you please let me know whether this does or
does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 14W- 111 (Killian Hall) and South Wing West
> Date: 11/10/2003
> Day: Monday
> Time: 7 AM - 9 AM
> System: Air Handler 4 and 5
> Duration: 2 hours
> Reason:
> Control System Upgrade.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in the
> above-listed areas during the shutdown period as well as loss of
> monitoring same by the Operations Center. If there is a problem in these
> areas during the 2-hour Control System Upgrade - please dial the a-zone
> at x8-9423 to report it. Thank you.
>
>