[68671] in Hotline Meeting
Bldg 33 - Air Handler/Supply Fan 2 Preventive Maintenace Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 2 09:22:38 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71AA8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
"'edorsch@mit.edu'" <edorsch@mit.edu>,
"'gallant@mit.edu'"
<gallant@mit.edu>,
"'graposa@MIT.EDU'" <graposa@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@mit.edu>,
"'src@mit.edu'" <src@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 2 Oct 2003 09:21:41 -0400
> To: B-Zone; Cust-Coach; edorsch@mit.edu; gallant@mit.edu;
> graposa@MIT.EDU; schedule@mit.edu; sdl-adm-lib@mit.edu; src@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg 33 - Air Handler/Supply Fan 2 Preventive Maintenace
> Shutdown Request
>
>
The following air handler/supply fan 2 preventive maintenance shutdown
request for Bldg. 33 - West Side on Thursday, October 9 is for your
information and comment. Would you please let me know whether this does or
does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 33 - West Side
> Date: 10/9/2003
> Day: Thursday
> Time: 7:30 AM - 11:30 AM
> System: Air Handler/Supply Fan 2
> Duration: 4 hours
> Reason:
> Perform preventive maintenance work on Air Handler/Supply Fan 2.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in the
> above-mentione areas during the 4-hour preventive maintenance shutdown
> period.
>
>