Bldg. 66 - Revised Asbestos Removal Notification

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 26 09:13:37 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D71A4C@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "Joseph Vella, Jr." <jpvella@PLANT.MIT.EDU>,
        Richard Hadge
	 <rhadge@PLANT.MIT.EDU>,
        Plant-Asbestos <plant-asbestos@mit.edu>, A-Zone
	 <A-Zone@mit.edu>,
        Cust-Coach <cust-coach@mit.edu>,
        "'haverty@mit.edu'"
	 <haverty@mit.edu>,
        "'kkgleasn@mit.edu'" <kkgleasn@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'swetzel@mit.edu'"
	 <swetzel@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'dcosta@mit.edu'" <dcosta@mit.edu>,
        "'johnnyd@mit.edu'"
	 <johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        Operators
	 <Operators@PLANT.MIT.EDU>,
        "'patriotabate@aol.com'"
	 <patriotabate@aol.com>
Date: Fri, 26 Sep 2003 09:13:06 -0400

> To: 	Joseph Vella, Jr.; Richard Hadge; Plant-Asbestos; A-Zone;
> Cust-Coach; haverty@mit.edu; kkgleasn@mit.edu; schedule@mit.edu;
> swetzel@mit.edu; shutdowns@mit.edu; dcosta@mit.edu; johnnyd@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators;
> patriotabate@aol.com
> Subject: 	Bldg. 66 - Revised Asbestos Removal Notification
> 
> 
The following revised asbestos removal notification for Bldg 66 - 1st, 3rd,
4th and 5th floors now at 5 PM on Friday, October 3 to 12 Noon on Sunday,
October 5 is for your information.  If you have any questions about this,
please feel free to contact me either by return e-mail or telephone.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 66 - 1st, 3rd, 4th and 5th floors
> Date: 10/3/2003
> Day: Friday
> Time: 5 PM (10/3) - 12 noon or so  Sunday, 10/5)
> System: None - asbestos removal notification
> Duration: 43 hours
> Reason: 
> Must remove and replace 200 square feet (patches of floor tiles and
> mastic) in the above-listed areas.
> 
> Effect: 
> Each area will be cordoned off during the asbestos removal period.
> 
> 