Bldg. 48 - Air Handler/Supply Fan 4 Shutdown/Filter Change Reques

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 24 09:06:17 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D71A25@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'mistetri@mit.edu'" <mistetri@MIT.Edu>,
        "'schedule@mit.edu'"
	 <schedule@MIT.Edu>,
        "'sfrankel@mit.edu'" <sfrankel@MIT.Edu>,
        "'jengle@mit.edu'" <jengle@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 24 Sep 2003 08:58:52 -0400

> To: 	B-Zone; Cust-Coach; mistetri@mit.edu; schedule@mit.edu;
> sfrankel@mit.edu; jengle@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 48 - Air Handler/Supply Fan 4 Shutdown/Filter Change
> Request
> 
> 
The following air handler/supply fan 4 shutdown/filter change request for
Bldg. 48 on Thursday, 9/25 is for your information.  Would you please let me
know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 48
> Date: 9/25/2003
> Day: Thursday
> Time: 10 AM - 10:30 AM
> System: Air Handler/Supply Fan 4 - PM#702640
> Duration: 1/2 hour
> Reason: 
> Filter Changes.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in Bldg. 48
> during the 30 minute shutdown/filter change period.
> 
> 