[68398] in Hotline Meeting
Bldg. E34 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 19 13:12:12 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D719D4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.Edu>, "'jsachs@mit.edu'" <jsachs@MIT.Edu>,
"'politano@mit.edu'" <politano@MIT.Edu>,
"'wendell@mit.edu'"
<wendell@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 19 Sep 2003 13:10:35 -0400
> To: E-Zone; jsachs@mit.edu; politano@mit.edu; wendell@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E34 - Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. E34 - 2nd floor only
on Tuesday, 9/23 is for your information and comment. Would you please let
me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E34 - 2nd floor only
> Date: 9/23/2003
> Day: Tuesday
> Time: 6 AM - 9 AM
> System: Chilled Water
> Duration: 3 hours
> Reason:
> Tie-in new fan coil units in E34 - 230.
>
> Effect:
> Loss of chilled water (air conditioning) and supply cooling (via ceiling
> supply fans) in E34 - 2nd floor during the 3-hour shutdown period.
>
>