Bldg. 8 - Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 19 11:47:01 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D719CA@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'carolr@mit.edu'" <carolr@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, "'ghughes@mit.edu'" <ghughes@MIT.Edu>,
        "'glabonte@mit.edu'" <glabonte@MIT.Edu>,
        "'lechtman@mit.edu'"
	 <lechtman@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 19 Sep 2003 11:45:36 -0400

> To: 	C-Zone; carolr@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; lechtman@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 8 - Chilled Water Shutdown Request
> 
> 
The following chilled water shutdown request for Bldg 8 - All on Wednesday,
9/24 is for your information and comment.  Would you please let me know
whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 8
> Date: 9/24/2003
> Day: Wednesday
> Time: 5 AM - 9 AM
> System: Chilled Water
> Duration: 4 hours
> Reason: 
> Install isolation valves for new Van Vliet Lab - 8 - 212 and 214.
> 
> Effect: 
> Loss of chilled water (air conditioning) and supply cooling via ceiling
> supply fans in Bldg. 8 during the shutdown period.
> 
> 