[67615] in Hotline Meeting
Bldg. 54 - Air Handler/Supply Fan 2 Shutdown/Filter Change Reque
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 21 12:57:43 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F24F3@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'graposa@MIT.EDU'" <graposa@MIT.Edu>,
"'kvkeefe@mit.edu'"
<kvkeefe@MIT.Edu>,
"'politano@mit.edu'" <politano@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@MIT.Edu>,
"'w1mx-officers@mit.edu'" <w1mx-officers@MIT.Edu>,
"'wendell@mit.edu'" <wendell@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 21 Aug 2003 12:53:57 -0400
> To: A-Zone; Cust-Coach; graposa@MIT.EDU; kvkeefe@mit.edu;
> politano@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> w1mx-officers@mit.edu; wendell@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 54 - Air Handler/Supply Fan 2 Shutdown/Filter Change
> Request
>
>
The following air handler/supply Fan 2 shutdown/filter change request for
Bldg 54 - South Zone on Monday, August 25 is for your information and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 54 - South Zone
> Date: 8/25/2003
> Day: Monday
> Time: 9 AM - 9:30 AM
> System: Air Handler/Supply Fan 2 - PM#700824
> Duration: 1/2 hour
> Reason:
> Bag filter changes.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in Bldg. 54
> - South Zone during the 30 minute shutdown/filter change period.
>
>