Bldg. 31 - Extended Building Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 11 10:55:57 2003

Message-ID: <568F0AEE7A57D511923900508B556451023F2461@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'gallant@mit.edu'" <gallant@MIT.Edu>,
        "'jmletend@mit.edu'"
	 <jmletend@MIT.Edu>,
        "'rcf@space.mit.edu'" <rcf@space.mit.edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'thane@mit.edu'"
	 <thane@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 11 Aug 2003 10:55:46 -0400

> To: 	B-Zone; Cust-Coach; gallant@mit.edu; jmletend@mit.edu;
> rcf@space.mit.edu; schedule@mit.edu; thane@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 31 - Extended Building Power Shutdown Request
> 
> 
The following extended building power shutdown request for Bldg. 31 - 053,
ground floor and part of the second floor on Thursday, August 14 PM to
Friday, August 15 AM is for your information and comment.  Would you please
let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872


> Status: Normal
> Building: 31 - 053; Ground Floor and part of 2nd floor
> Date: 8/14/2003
> Day: Thursday
> Time: 9 PM (8/14) - 7 AM (8/15)
> System: Building Power
> Duration: 10 hours
> Reason: 
> Change-out and relocate 4 power panels in room 053.
> 
> Effect: 
> Loss of building power in the above-mentioned areas during the shu
> 
> 