[67413] in Hotline Meeting
Bldg. 10 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 11 10:02:20 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F245F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'aruspice@mit.edu'" <aruspice@mit.edu>, C-Zone <C-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'dfucillo@mit.edu'" <dfucillo@mit.edu>,
"'dhelman@mit.edu'" <dhelman@mit.edu>,
"'emmarogers@mit.edu'"
<emmarogers@mit.edu>,
"'esdeb@mit.edu'" <esdeb@mit.edu>,
"'granvill@mit.edu'" <granvill@mit.edu>,
"'graposa@MIT.EDU'"
<graposa@mit.edu>,
"'jhlyons@mit.edu'" <jhlyons@mit.edu>,
"'jobrien@mit.edu'" <jobrien@mit.edu>,
"'kates@mit.edu'" <kates@mit.edu>, "'lkn@mit.edu'" <lkn@mit.edu>,
"'lsc@mit.edu'" <lsc@mit.edu>, "'marsha5@mit.edu'" <marsha5@mit.edu>,
"'mdhinkle@mit.edu'"
<mdhinkle@mit.edu>,
"'mleen@mit.edu'" <mleen@mit.edu>, "'ndk@mit.edu'"
<ndk@mit.edu>,
"'rrhonda@mit.edu'" <rrhonda@mit.edu>,
"'ryan@mit.edu'"
<ryan@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sdl-adm-lib@mit.edu'" <sdl-adm-lib@mit.edu>,
"'tkeim@mit.edu'"
<tkeim@mit.edu>, "'jgk@mit.edu'" <jgk@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 11 Aug 2003 10:01:16 -0400
> To: aruspice@mit.edu; C-Zone; Cust-Coach; shutdowns@mit.edu;
> dfucillo@mit.edu; dhelman@mit.edu; emmarogers@mit.edu; esdeb@mit.edu;
> granvill@mit.edu; graposa@MIT.EDU; jhlyons@mit.edu; jobrien@mit.edu;
> kates@mit.edu; lkn@mit.edu; lsc@mit.edu; marsha5@mit.edu;
> mdhinkle@mit.edu; mleen@mit.edu; ndk@mit.edu; rrhonda@mit.edu;
> ryan@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu; tkeim@mit.edu;
> jgk@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 10 - Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. 10 on Wednesday,
August 13 is for your review and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 10
> Date: 8/13/2003
> Day: Wednesday
> Time: 6 AM - 9 AM
> System: Chilled Water (Air Conditioning)
> Duration: 3 hours
> Reason:
> Replace Air Handler 4 isolation valves - services room 105
>
> Effect:
> Loss of chilled water (air conditioning) in all of Bldg. 10 during the
> 3-hour early morning shutdown period.
>
>