[67177] in Hotline Meeting
Bldg 8 building power shutdown request for 8/2/03
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Jul 28 12:11:01 2003
Message-ID: <568F0AEE7A57D511923900508B556451035618E0@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, carolr@MIT.Edu, Cust-Coach
<cust-coach@MIT.Edu>,
ghughes@MIT.Edu, glabonte@MIT.Edu, lechtman@MIT.Edu, schedule@MIT.Edu,
shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU, rm-shutdown@MIT.Edu
Date: Mon, 28 Jul 2003 12:10:50 -0400
> To: C-Zone; carolr@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; lechtman@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg 8 building power shutdown request for 8/2/03
>
>
The following shutdown request is for building 8 on 8/2/03. Could you
please let me know if this does or does not meet with your approval?
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Normal
> Building: 8
> Date: 8/2/2003
> Day: Saturday
> Time: 6 am - 12 am
> System: Building 8 building power all normal power 120 - 208 v
> Duration: 18 hours
> Reason:
> Relocating a first floor electrical closet.
>
> Effect:
> There will be a loss of all building power during this time.
>
>