[61023] in Hotline Meeting
Bldg. 12 - Chilled Water/Supply Cooling Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 28 13:10:37 2002
Message-ID: <568F0AEE7A57D511923900508B5564510123256A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jbartels@MIT.EDU'" <jbartels@MIT.EDU>,
"'jcentor@mit.edu'"
<jcentor@MIT.EDU>,
"'rigione@mit.edu'" <rigione@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
C-Zone
<C-Zone@MIT.EDU>
Date: Wed, 28 Aug 2002 13:10:34 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: jbartels@MIT.EDU; jcentor@mit.edu; rigione@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; C-Zone
> Subject: Bldg. 12 - Chilled Water/Supply Cooling Shutdown Request
>
>
The following chilled water/supply cooling shutdown request for Bldg. 12 -
011D, 056 (ovens) and 182 on Tuesday, 9/3is for your review and comment.
Would you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 12 - 011A, 056 (ovens) and 182
> Date: 9/3/2002
> Day: Tuesday
> Time: 7:30 AM - 9:30 AM
> System: Chilled Water Pump #707214/Air Handler 2
> Duration: 2 hours
> Reason:
> Check and clean strainer.
>
> Effect:
> Loss of chilled water/supply cooling in the above-mentioned areas during
> the 2-hour shutdown period.
>
>