[61022] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldgs. W34, W35, W45 and W53 Electrical Power Shutdown/Test

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 28 11:33:35 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232564@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bwc@mit.edu'" <bwc@mit.edu>, "'bwiget@mit.edu'" <bwiget@mit.edu>,
        D-Zone <D-Zone@mit.edu>, "'djmartin@mit.edu'" <djmartin@mit.edu>,
        "'slett@mit.edu'" <slett@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>,
        "'nmagnuso@mit.edu'" <nmagnuso@mit.edu>,
        "'jmcd@mit.edu'" <jmcd@mit.edu>,
        "'lrbrutti@mit.edu'" <lrbrutti@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 28 Aug 2002 11:33:33 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	bwc@mit.edu; bwiget@mit.edu; D-Zone; djmartin@mit.edu;
> slett@mit.edu; shutdowns@mit.edu; nmagnuso@mit.edu; jmcd@mit.edu;
> lrbrutti@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. W34, W35, W45 and W53 Electrical Power Shutdown/Test
> 
> 
The following electrical power shtudown/test for Bldgs. W34, W35, W45 and
W53 on Thursday, 8/29 is for your information and comment.  Would you please
let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: W34, W35, W45 and W53
> Date: 8/29/2002
> Day: Thursday
> Time: 6 AM - 7 AM
> System: Electrical Power
> Duration: 1 hour
> Reason: 
> Test emergency genenerator which will remain on for all buildings during
> City of Cambridge Electrical Dept. walk through.
> 
> Effect: 
> Loss of building power during the 1-hour testing period.
> 
> 

home help back first fref pref prev next nref lref last post