[60681] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 66 - Rescheduled Approved Chilled Water Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 7 09:15:18 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232429@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: George Stangas <gstangas@PLANT.MIT.EDU>, RM-HvacSys
	 <rm-hvacsys@mit.edu>,
        "'ghand@mit.edu'" <ghand@mit.edu>,
        "'johnnyd@mit.edu'" <johnnyd@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
        "'haverty@mit.edu'" <haverty@mit.edu>, "'kkg@mit.edu'" <kkg@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'swetzel@mit.edu'"
	 <swetzel@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        Billy Homeyer
	 <whomeyer@PLANT.MIT.EDU>, A-Zone <A-Zone@mit.edu>
Date: Wed, 7 Aug 2002 09:15:14 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	George Stangas; RM-HvacSys; ghand@mit.edu; johnnyd@mit.edu;
> Cust-Coach; haverty@mit.edu; kkg@mit.edu; schedule@mit.edu;
> swetzel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Billy Homeyer; A-Zone
> Subject: 	Bldg. 66 - Rescheduled Approved Chilled Water Shutdown
> 
> 
The following approved rescheduled chilled water shutdown for Bldg. 66 now
on Saturday, August 3 is for your information.

Thank you

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 66
> Date: 8/10/2002
> Day: Saturday
> Time: 6 AM - 6 PM
> System: Chilled Water (shutdown from 56 stairwell)
> Duration: 12 hours
> Reason: 
> Tie-in new piping to 6" main in Rm. 253 and in the subbsement.
> 
> Effect: 
> Loss of chilled water (air conditioning), supply ventilation and supply
> cooling during the 12-hour shutdown period.
> 
> 

home help back first fref pref prev next nref lref last post