[60537] in Hotline Meeting
Bldg. 5 and 7 - Rescheduled Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 31 08:14:38 2002
Message-ID: <568F0AEE7A57D511923900508B556451012323A9@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mamullow@mit.edu'" <mamullow@mit.edu>,
"'hlbroderick@mit.edu'"
<hlbroderick@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
C-Zone
<C-Zone@mit.edu>, Raul Varela <Varela@PLANT.MIT.EDU>
Date: Wed, 31 Jul 2002 08:14:34 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: mamullow@mit.edu; hlbroderick@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; C-Zone; Raul Varela
> Subject: Bldg. 5 and 7 - Rescheduled Chilled Water Shutdown Request
>
>
The following chilled water shutdown for Bldg. 5 - 301 through 326 and 7 -
321 on Thursday, August 1 is again for your review and comments. Would you
please let me know if this revised shutdown meets with your approval or does
not.
Thanks again for your time.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 5 - 301 thru 326 and 7 - 321
> Date: 8/1/2002
> Day: Thursday
> Time: 6 AM - 10 AM
> System: Chilled Water
> Duration: 4 hours
> Reason:
> Tie in new fan coil units.
>
> Effect:
> Loss of chilled water in the above listed buildings and rooms during the
> 4-hour shutdown period.
>
>