Re: Bldg. E40 - Rescheduled Supply Ventilation/Supply Cooling

daemon@ATHENA.MIT.EDU (Ellen Baum)
Wed Jul 31 08:11:14 2002

Message-Id: <4.3.2.7.2.20020731080855.015ff010@po14.mit.edu>
Date: Wed, 31 Jul 2002 08:11:30 -0400
To: Andrea Nichols <andrea@PLANT.MIT.EDU>
From: Ellen Baum <ebaum@MIT.EDU>
Cc: E-Zone <E-Zone@MIT.EDU>, "'gwj@mit.edu'" <gwj@MIT.EDU>,
        "'ebaum@mit.edu'" <ebaum@MIT.EDU>,
        "'mityler@mit.edu'" <mityler@MIT.EDU>, "'jfob@mit.edu'" <jfob@MIT.EDU>,
        "'jys@mit.edu'" <jys@MIT.EDU>, "'kelley@mit.edu'" <kelley@MIT.EDU>,
        "'lambert@mit.edu'" <lambert@MIT.EDU>,
        "'lrose@mit.edu'" <lrose@MIT.EDU>,
        "'rklester@mit.edu'" <rklester@MIT.EDU>,
        "'pmosley@mit.edu'" <pmosley@MIT.EDU>,
        "'jdalton@mit.edu'" <jdalton@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'hastings@mit.edu'" <hastings@MIT.EDU>,
        "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
In-Reply-To: <568F0AEE7A57D511923900508B556451012323A7@PLANT.MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"; format=flowed

My office needs more than one day's notice.  There are employees that have 
interior offices that could not work without the air supply.  Could you 
suggest a time frame that is longer  than one day for which I can plan to 
shut the office down.   Also, I could not determine what 3 hour window you 
were referring to. Thanks.



At 07:40 AM 7/31/2002 -0400, Andrea Nichols wrote:
> > To:   E-Zone; gwj@mit.edu; ebaum@mit.edu; mityler@mit.edu; jfob@mit.edu;
> > jys@mit.edu; kelley@mit.edu; lambert@mit.edu; lrose@mit.edu;
> > rklester@mit.edu; pmosley@mit.edu; jdalton@mit.edu; shutdowns@mit.edu;
> > hastings@mit.edu
> > Cc:   shutdown@plant.mit.edu
> > Subject:      Bldg. E40 - Rescheduled Supply Ventilation/Supply Cooling
> > Shutdown Request
> >
> >
>The following rescheduled supply ventilation/supply cooling shutdown request
>for Bldg. E40 on Thursday, Augsut 1 is for your review and comment.  Would
>you please let me know whether this does or does not meet with your
>approval.
>
>Thank you again for your time.
>
>Andrea Nichols
>Repair and Maintenance
>8-7872
>
> > Status: Normal
> > Building: E40
> > Date: 8/1/2002
> > Day: Thursday
> > Time: 7 AM - 10 AM
> > System: Supply Ventilation/Supply Cooling
> > Duration: 3 hours
> > Reason:
> > Control System Upgrade
> >
> > Effect:
> > Loss of supply ventilation and supply cooling during the 3-hour shutdown