[58882] in Hotline Meeting
Bldg. 16 - Critical Steam Station Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Apr 1 14:33:55 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231CCB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'bengel@mit.edu'" <bengel@MIT.Edu>,
"'carolr@mit.edu'" <carolr@MIT.Edu>,
"'cbutters@mit.edu'"
<cbutters@MIT.Edu>,
"'childs@mit.edu'" <childs@MIT.Edu>, Cust-Coach
<cust-coach@MIT.Edu>,
"'daczel@mit.edu'" <daczel@MIT.Edu>,
"'ehendrix@mit.edu'" <ehendrix@MIT.Edu>, "'frc@mit.edu'" <frc@MIT.Edu>,
"'ghughes@mit.edu'" <ghughes@MIT.Edu>,
"'gibbhen@mit.edu'"
<gibbhen@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'goodluck@mit.edu'" <goodluck@MIT.Edu>,
"'jmganno@mit.edu'"
<jmganno@MIT.Edu>,
"'kreposa@mit.edu'" <kreposa@MIT.Edu>,
"'lechtman@mit.edu'" <lechtman@MIT.Edu>,
"'mgray@mit.edu'"
<mgray@MIT.Edu>,
"'mjudge@mit.edu'" <mjudge@MIT.Edu>,
"'rosieb@mit.edu'"
<rosieb@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'steve@hstbme.mit.edu'" <steve@hstbme.mit.edu>,
"'tquinn@mit.edu'"
<tquinn@MIT.Edu>,
"'trometer@mit.edu'" <trometer@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 1 Apr 2002 14:33:50 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; bengel@mit.edu; carolr@mit.edu; cbutters@mit.edu;
> childs@mit.edu; Cust-Coach; daczel@mit.edu; ehendrix@mit.edu; frc@mit.edu;
> ghughes@mit.edu; gibbhen@mit.edu; glabonte@mit.edu; goodluck@mit.edu;
> jmganno@mit.edu; kreposa@mit.edu; lechtman@mit.edu; mgray@mit.edu;
> mjudge@mit.edu; rosieb@mit.edu; schedule@mit.edu; steve@hstbme.mit.edu;
> tquinn@mit.edu; trometer@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 16 - Critical Steam Station Shutdown Request
>
>
The following Critical steam station shutdown request for Bldg. 16 on
Thursday, 4/4 is for your review and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Critical
> Building: 16
> Date: 4/4/2002
> Day: Thursday
> Time: 8:30 AM - 2:30 PM
> System: Steam Station (Flange)
> Duration: 6 hours
> Reason:
> To repair leak - medium pressure flange.
>
> Effect:
> Loss of medum and low pressure steam. This means there will be no hot
> domestic water (for bathroom, kitchen and lab sink faucets), hot lab
> process water (for lab equipment) or heating hot water (perimeter building
> steam heat) during the shutdown period.
>
>