Bldg. 18 - Critical Building Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 7 10:02:43 2002

Message-ID: <568F0AEE7A57D511923900508B5564511563EB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rjwilk@mit.edu'" <rjwilk@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 7 Feb 2002 10:02:40 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	rjwilk@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 18 - Critical Building Power Shutdown Request
> 
> 
The following Critical building power shutdown request for Bldg. 18 -
Subbasement Labs and PMI on Monday, 2/11 is for your review and comment.
Would you please let me know whether this does or does not meet with your
approval.

Thank you Richard.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Critical
> Building: 18 - subbasement labs and PMI
> Date: 2/11/2002
> Day: Monday
> Time: 6 AM - 8 AM
> System: Building Power - 120  - 208 V
> Duration: 2 hours
> Reason: 
> Swapping feeds to power panels.
> 
> Effect: 
> Loss of building power in 18 - subbasement labs and PMI during the 2-hour
> shutdown epriod.
> 
> 