Bldg. 10 - Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 14 15:24:52 2001

Message-ID: <568F0AEE7A57D511923900508B556451155F3E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'aruspice@mit.edu'" <aruspice@mit.edu>, C-Zone <C-Zone@mit.edu>,
        Cust-Coach <cust-coach@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
        "'dfucillo@mit.edu'" <dfucillo@mit.edu>,
        "'engler@mitvma.mit.edu'"
	 <engler@mitvma.mit.edu>,
        "'fin@mit.edu'" <fin@mit.edu>, "'granvill@mit.edu'" <granvill@mit.edu>,
        "'honda@mit.edu'"
	 <honda@mit.edu>,
        "'jhlyons@mit.edu'" <jhlyons@mit.edu>,
        "'jobrien@mit.edu'" <jobrien@mit.edu>,
        "'kates@mit.edu'" <kates@mit.edu>, "'lkn@mit.edu'" <lkn@mit.edu>,
        "'lsandler@mit.edu'" <lsandler@mit.edu>, "'lsc@mit.edu'" <lsc@mit.edu>,
        "'mleen@mit.edu'" <mleen@mit.edu>, "'ndk@mit.edu'" <ndk@mit.edu>,
        "'rrhonda@mit.edu'" <rrhonda@mit.edu>, "'ryan@mit.edu'" <ryan@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'sdl-adm-lib@mit.edu'" <sdl-adm-lib@mit.edu>,
        "'sexton@mit.edu'"
	 <sexton@mit.edu>,
        "'sgass@mit.edu'" <sgass@mit.edu>, "'tkeim@mit.edu'"
	 <tkeim@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'jdb@mit.edu'" <jdb@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 14 Nov 2001 15:24:37 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	aruspice@mit.edu; C-Zone; Cust-Coach; Cust-Coach; dfucillo@mit.edu;
> engler@mitvma.mit.edu; fin@mit.edu; granvill@mit.edu; honda@mit.edu;
> jhlyons@mit.edu; jobrien@mit.edu; kates@mit.edu; lkn@mit.edu;
> lsandler@mit.edu; lsc@mit.edu; mleen@mit.edu; ndk@mit.edu;
> rrhonda@mit.edu; ryan@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> sexton@mit.edu; sgass@mit.edu; tkeim@mit.edu; shutdowns@mit.edu;
> jdb@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 10 - Chilled Water Shutdown Request
> 
> 
The following chilled water shutdown request for Blg. 10 - 249, 250, 253,
255, 259, 260, 261, 265, 266 and 270 on Friday, 11/16 is for your
information and comment.  Would you please let me know whether this does or
does not have your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 10 - 259, 250, 253, 255, 259, 260, 261, 265, 266 and 270
> Date: 11/16/2001
> Day: Friday
> Time: 3 PM - 8 PM
> System: Chilled Water
> Duration: 5 hours
> Reason: 
> Replace valves; install flush valves.
> 
> Effect: 
> Loss of chilled water (air conditioning) in the above listed rooms during
> the shutdown period.
> 
> 