[55693] in Hotline Meeting
Re: Bldg. E23 Fire Protection Water Shutdown Request
daemon@ATHENA.MIT.EDU (Rodney Edwards)
Fri Jul 20 08:55:59 2001
Message-Id: <sb57f1c7.043@med.mit.edu>
Date: Fri, 20 Jul 2001 08:54:13 -0400
From: "Rodney Edwards" <EDWA@med.mit.edu>
To: "Cathleen Dwyer" <DWYE@med.mit.edu>, "Anthony Rogers" <ROGE@med.mit.edu>,
<shutdowns@mit.edu>, <andrea@PLANT.MIT.EDU>
Cc: <shutdown@PLANT.MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset=US-ASCII
Content-Disposition: inline
Content-Transfer-Encoding: 8bit
Ok...Rodney Edwards E23 All.
>>> Andrea Nichols <andrea@PLANT.MIT.EDU> 07/20/01 08:42AM >>>
> To: dwye@med.mit.edu; edwa@med.mit.edu; roge@med.mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E23 Fire Protection Water Shutdown Request
>
>
The following fire protection water shutdown request for Bldg. E23 - 5th
floor on Wednesday, July 25 is for your information and comment. Would you
please let me know whether this does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E23 - 5th floor and rest of building
> Date: 7/25/2001
> Day: Wednesday
> Time: 8:30 AM - 4:30 PM
> System: Fire Protection Water
> Duration: 8 hours
> Reason:
> Relocate sprinkler heads in E23 - 5th floor.
>
> Effect:
> Loss of fire protection water in all of E23 during the shutdown period.
> The Safety Office will be advised of this - that office will notify the
> Fire Department.
>
>