Bldg. W32 - Asbestos Removal/Shutdown Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 12 08:57:40 2001
Message-ID: <568F0AEE7A57D511923900508B556451155775@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'wc@mit.edu'" <wc@mit.edu>, "'bwiget@mit.edu'" <bwiget@mit.edu>,
D-Zone <D-Zone@mit.edu>, "'djmartin@mit.edu'" <djmartin@mit.edu>,
"'slett@mit.edu'" <slett@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'mmahoney@mit.edu'" <mmahoney@mit.edu>, "'tr6@mit.edu'" <tr6@mit.edu>,
"'jdoucett@mit.edu'" <jdoucett@mit.edu>,
"'tdoyle@mit.edu'" <tdoyle@mit.edu>,
Paul Stordy <PStordy@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Thu, 12 Jul 2001 08:56:20 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: wc@mit.edu; bwiget@mit.edu; D-Zone; djmartin@mit.edu; slett@mit.edu;
> shutdowns@mit.edu; mmahoney@mit.edu; tr6@mit.edu; jdoucett@mit.edu;
> tdoyle@mit.edu; Paul Stordy
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. W32 - Asbestos Removal/Shutdown Notification
>
>
The following asbestos removal/all steam shutdown notification for Bldg. W32
on Saturday, July 21 and Sunday, 7/22 is for your information. If you have
any question about this, please contact Tammy Doyle at 3-5166.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: W32
> Date: 7/21/2001
> Day: Saturday
> Time: 7 - 4 PM on 7/21 and 7/22
> System: All Steam Shutdown and asbestos removal notification
> Duration: 9 hours each day for total of 18 hours
> Reason:
> Removal of 40 linear feet of tile in the steam station.
>
> Effect:
> No access to Bldg. W32 Mechanic Room. Loss of all steam in Bldg. W32. This
> means there will be no hot domestic water for bathroom or kitchen sinks
> during the shutdown period..
>
>