Re: Shutdown request for building 2 on 7/10

daemon@ATHENA.MIT.EDU (Camille Capozzi Carino)
Thu Jul 5 13:13:55 2001

Date: Thu, 5 Jul 2001 13:13:46 -0400 (EDT)
From: Camille Capozzi Carino <capozzi@math.mit.edu>
To: Dawn Simonelli <dsimone@plant.mit.edu>
cc: C-Zone <C-Zone@mit.edu>, <crg@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
        <duggins@math.mit.edu>, <mbj@mit.edu>, <rjwilk@mit.edu>,
        <schedule@mit.edu>, <sdimond@mit.edu>, <shutdowns@mit.edu>,
        <shutdown@plant.mit.edu>
In-Reply-To: <568F0AEE7A57D511923900508B5564513F4D32@PLANT.MIT.EDU>
Message-ID: <Pine.GSO.4.33.0107051313280.19314-100000@fermat.mit.edu>
MIME-Version: 1.0
Content-Type: TEXT/PLAIN; charset=US-ASCII


The shutdown is fine with us.  Many thanks!
Camille

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Camille Capozzi Carino
Office/Personnel Manager
M.I.T., Department of Mathematics Headquarters
Building 2, Room 236					Voice (617) 253-4382
77 Massachusetts Avenue				FAX (617) 253-4358
Cambridge, MA 02139-4307		e-mail:  capozzi@math.mit.edu
                           	WWW:  http://www-math.mit.edu/hq/
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


On Thu, 5 Jul 2001, Dawn Simonelli wrote:

> > To: 	C-Zone; capozzi@math.mit.edu; crg@mit.edu; Cust-Coach;
> > duggins@math.mit.edu; mbj@mit.edu; rjwilk@mit.edu; schedule@mit.edu;
> > sdimond@mit.edu; shutdowns@mit.edu
> > Cc: 	shutdown@plant.mit.edu
> > Subject: 	Shutdown request for building 2 on 7/10
> >
> >
> The following shutdown request is for building 2 rooms 033 and 037 on July
> 10.  Please let me know if this does or does not meet with your approval.
>
> Thank you
> Dawn Simonelli
> Repair and Maintenance
> 2-1599
>
> > Status: Normal
> > Building: 2 rooms 033 and 037
> > Date: 7/10/01
> > Day: Tuesday
> > Time: 7:30 AM - 11:30 AM
> > System: Chilled water
> > Duration: 4 hours
> > Reason:
> > There is a blockage in the supply line.
> >
> > Effect:
> > There will be a loss of chilled water and supply ventilation air.
> >
> >
>