[55533] in Hotline Meeting
Emergency shutdown for building 54 floors 1-18 even number rooms
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Jul 5 12:40:23 2001
Message-ID: <568F0AEE7A57D511923900508B5564513F4D60@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: Operators <Operators@PLANT.MIT.EDU>, Warren Scott
<WScott@PLANT.MIT.EDU>,
A-Zone <A-Zone@MIT.Edu>, Cust-Coach
<cust-coach@MIT.Edu>,
kvkeefe@MIT.Edu, politano@MIT.Edu, schedule@MIT.Edu,
sdl-adm-lib@MIT.Edu, w1mx-officers@MIT.Edu, wendell@MIT.Edu,
shutdowns@MIT.Edu, cp-command@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Thu, 5 Jul 2001 12:38:54 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: Operators; Warren Scott; A-Zone; Cust-Coach; kvkeefe@mit.edu;
> politano@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> w1mx-officers@mit.edu; wendell@mit.edu; shutdowns@mit.edu;
> cp-command@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Emergency shutdown for building 54 floors 1-18 even number
> rooms only.
>
>
The following emergency shutdown for building 54 floors 1-18 even number
rooms on the south side only from now unti 7/6 is for your information.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Emergency
> Building: 54 floors 1-18 (even numbered rooms on the south side)
> Date: 7/5/01
> Day: Thursday
> Time: Unknown
> System: Air Handler 2
> Duration: Unknown
> Reason:
> The fan motor has burnto out and waiting on the replacement part.
>
> Effect:
> The fans will be down during this time.
>
>