Bldg. 16 - All Labs - Preventive Maintenance Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 24 09:24:27 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2528@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'bengel@mit.edu'" <bengel@MIT.Edu>,
"'carolr@mit.edu'" <carolr@MIT.Edu>,
"'cbates@mit.edu'" <cbates@MIT.Edu>,
"'cbutters@mit.edu'" <cbutters@MIT.Edu>,
"'childs@mit.edu'"
<childs@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'cwyckoff@mit.edu'"
<cwyckoff@MIT.Edu>,
"'daczel@mit.edu'" <daczel@MIT.Edu>, "'frc@mit.edu'"
<frc@MIT.Edu>,
"'gibbhen@mit.edu'" <gibbhen@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'goodluck@mit.edu'"
<goodluck@MIT.Edu>,
"'jmganno@mit.edu'" <jmganno@MIT.Edu>,
"'kreposa@mit.edu'" <kreposa@MIT.Edu>,
"'lechtman@mit.edu'"
<lechtman@MIT.Edu>,
"'mgray@mit.edu'" <mgray@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'steve@hstbme.mit.edu'"
<steve@hstbme.mit.edu>,
"'trometer@mit.edu'" <trometer@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 24 May 2001 09:24:21 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; bengel@mit.edu; carolr@mit.edu; cbates@mit.edu;
> cbutters@mit.edu; childs@mit.edu; Cust-Coach; cwyckoff@mit.edu;
> daczel@mit.edu; frc@mit.edu; gibbhen@mit.edu; glabonte@mit.edu;
> goodluck@mit.edu; jmganno@mit.edu; kreposa@mit.edu; lechtman@mit.edu;
> mgray@mit.edu; schedule@mit.edu; steve@hstbme.mit.edu; trometer@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 16 - All Labs - Preventive Maintenance Shutdown
> Request
>
>
The following preventive maintenance shutdown request for Bldg. 16 - All
Labs on Thursday, 5/31 is for your review and comment. Would you please let
me know whether this does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 16 - All Labs
> Date: 5/31/2001
> Day: Thursday
> Time: 7 AM - 11 AM
> System: Air Handler2 - supply fan 1/Air Handler 2 - supply fan 2
> Duration: 4 hours
> Reason:
> Preventive maintenance work on PM#718767 (Air Handler 2-1) and #718768 -
> Air Handler 2-2.
>
> Effect:
> Loss of supply ventilation, supply cooling/supply heating in Bldg. 16 Labs
> during the shutdown period.
>
>