[55169] in Hotline Meeting
Bldg. 8 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 24 08:48:01 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2525@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'carolr@mit.edu'" <carolr@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>,
"'cwyckoff@mit.edu'" <cwyckoff@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'kmartel@mit.edu'"
<kmartel@MIT.Edu>,
"'lechtman@mit.edu'" <lechtman@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>,
"'opsnote@mit.edu'" <opsnote@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 24 May 2001 08:47:55 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; carolr@mit.edu; Cust-Coach; cwyckoff@mit.edu;
> glabonte@mit.edu; kmartel@mit.edu; lechtman@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; opsnote@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 8 - Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. 8 - 401 thru 413,
402, 404, 408, 415 and 417T on Tuesday, 5/29 is for your information and
comment. Would you please let me know whether this does or does not have
your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 8 - 401 thru 413, 402, 404, 408, 415 and 417T
> Date: 5/29/2001
> Day: Tuesday
> Time: 7:30 AM - 2:30 PM
> System: Chilled Water
> Duration: 7 hours
> Reason:
> Tie in new fan coil units.
>
> Effect:
> Loss of chilled water - no cooling from fan coil units in the above listed
> rooms during the shutdown period.
>
>