[54942] in Hotline Meeting
Bldg. 9 - 235, 253, 250, 251, 313, 321, 323, 325, 327, 329, 335,
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 9 10:06:14 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD23F2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>
Date: Wed, 9 May 2001 10:06:04 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: shutdowns@mit.edu; schedule@mit.edu
> Cc:
> Subject: Bldg. 9 - 235, 253, 250, 251, 313, 321, 323, 325, 327, 329,
> 335, 355, 427, 449, 550, 551 and 552 - 5/10 - Rescheduled Chilled Water
> Shutdown Request
>
>
The following rescheduled Chilled Water shutdown request for Bldg. 9 - 235,
253, 250, 251, 313, 321, 323, 325, 327, 329, 335, 355, 427, 449, 550, 551
and 552 now on Thursday, May 10 is again for your review and comment. Would
you please let me know whether this new date does or does not have your
approval.
Thank you,
Andrea Nichols
Operations Center
8-7872
I apologize for the short notice. I thought you had received this notice
earlier and discovered you had not. Sorry again and thanks for your
response in advance.
Andrea
> Status: Critical
> Building: 9 - 235, 253, 250, 251, 313, 321, 323, 325, 327, 329, 335, 355,
> 427, 449, 550, 551 and 552
> Date: 5/10/2001
> Day: Thursday
> Time: 7:30 AM - 2:30 PM
> System: Chilled Water
> Duration: 7 hours
> Reason:
> Tie in new fan coil units.
>
> Effect:
> Loss of chille water in the above listed rooms only durin the shutdown
> period.
>
>