Bldg. 39 - 301 East and Clean Rooms (3/30 - 4/2) Supply Ventilat

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Mar 22 13:10:13 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD20B8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'mcgrath@mtl.mit.edu'" <mcgrath@mtl.mit.edu>,
        "'rcf@space.mit.edu'"
	 <rcf@space.mit.edu>,
        "'walsh@mtl.mit.edu'" <walsh@mtl.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 22 Mar 2001 13:10:03 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; mcgrath@mtl.mit.edu; rcf@space.mit.edu;
> walsh@mtl.mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 39 - 301 East and Clean Rooms (3/30 -  4/2) Supply
> Ventilation Shutdown Request
> 
> 
The following Supply Ventilation shutdown request for Blgd .39 - 301 East
and Clean Rooms on Friday, 3/30 up to Monday, 4/2 is for your information
and comment.  Would you please let me know whether this does or does not
meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 39 - 301 East and Clean Rooms
> Date: 3/30/2001
> Day: Friday
> Time: 6 PM (3/30) - 7 AM (4/2)
> System: Air Handler 1 
> Duration: 2 1/2 days
> Reason: 
> Relocate supply duct in 39-578.
> 
> Effect: 
> Loss of Air Handler 1 (supply ventilation) in 39-301 East and clean rooms
> during the shutdown period.
> 
> 