[54339] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 14 - Basement - 3/29 PM - 3/30 AM(Supply Ventilation, Suppl

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Mar 22 12:35:34 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD20B6@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'altenb@mit.edu'" <altenb@MIT.Edu>,
        "'bkdavis@mit.edu'" <bkdavis@MIT.Edu>,
        "'cpomieko@mit.edu'"
	 <cpomieko@MIT.Edu>,
        "'csnyder@mit.edu'" <csnyder@MIT.Edu>,
        Cust-Coach
	 <cust-coach@MIT.Edu>,
        "'edorsch@mit.edu'" <edorsch@MIT.Edu>,
        "'ellertsn@mit.edu'" <ellertsn@MIT.Edu>,
        "'fleish@mit.edu'"
	 <fleish@MIT.Edu>,
        "'jhlyons@mit.edu'" <jhlyons@MIT.Edu>, "'mosh@mit.edu'" <mosh@MIT.Edu>,
        "'nlowe@mit.edu'" <nlowe@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'sdl-adm-lib@mit.edu'"
	 <sdl-adm-lib@MIT.Edu>,
        "'slarkin@mit.edu'" <slarkin@MIT.Edu>,
        "'susanne@mit.edu'" <susanne@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 22 Mar 2001 12:35:20 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; altenb@mit.edu; bkdavis@mit.edu; cpomieko@mit.edu;
> csnyder@mit.edu; Cust-Coach; edorsch@mit.edu; ellertsn@mit.edu;
> fleish@mit.edu; jhlyons@mit.edu; mosh@mit.edu; nlowe@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; slarkin@mit.edu; susanne@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 14 - Basement - 3/29 PM - 3/30 AM(Supply Ventilation,
> Supply Cooling and Supply Heating Shutdown Request
> 
> 
The following Supply ventilation, supply cooling and supply heating shutdown
request for Bldg. 14 - Basement on Thursday, 3/29 PM to Friday, 3/30 AM is
for your review and comment.  Would you please let me know whether this does
or does not meet with your approval.

Thank you,

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 14 - Basement
> Date: 3/29/2001
> Day: Thursday
> Time: 10 PM (3/29) - 8 AM (3/30)
> System: Air Handler 2, Supply Fan 1, Return Fan 1
> Duration: 10 hours
> Reason: 
> Replace motor control and wiring for AH2, SF2 and RF.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in Bldg. 14
> Basement during the 10-hour shutdown period.
> 
> 