[54201] in Hotline Meeting
Bldg. 2 - 052, 066, 150, 250, 252, 254, 350, 348, 350J - 3/14 - R
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Mar 12 14:57:27 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2000@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mbj@mit.edu'" <mbj@mit.edu>, C-Zone <C-Zone@mit.edu>,
"'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
Cust-Coach
<cust-coach@mit.edu>,
"'duggins@math.mit.edu'" <duggins@math.mit.edu>,
"'rjwilk@mit.edu'" <rjwilk@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'sdimond@mit.edu'" <sdimond@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 12 Mar 2001 14:57:13 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: mbj@mit.edu; C-Zone; capozzi@math.mit.edu; Cust-Coach;
> duggins@math.mit.edu; rjwilk@mit.edu; schedule@mit.edu; sdimond@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 2 - 052, 066, 150, 250, 252, 254, 350, 348, 350J -
> 3/14 - Rescheduled Shutdown Request
>
>
Dear Everyone:
The following rescheduled shutdown request for Bldg. 2 - 052, 066, 150, 250,
252, 254, 350, 348, 350J now for Wednesday, 3/14 is again for your comments
and review. Would you please let me know whether this new date and
shortened time period have your approval or does not.
Thank you again for your time,
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 2 - 052, 066, 150, 250, 252, 254, 350, 348, 350J
> Date: 3/14/2001
> Day: Wednesday
> Time: 7 AM - 9:30 AM
> System: Domestic hot and cold water
> Duration: 2 1/2 hours
> Reason:
> Install two new ball valves.
>
> Effect:
> Loss of hot and cold domestic water in Bldg. 2. This means that no
> bathrooms (toilets, sink faucets) kitchen faucets or lab hot and cold
> water faucets will be operational during the shutdown period.
>
>