[53226] in Hotline Meeting
Shutdown request for building W13 on 12/26
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Dec 21 15:03:57 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451D2B6AB@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: kcn@MIT.EDU, mwhelan@MIT.EDU, schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: D-Zone <D-Zone@MIT.EDU>, shutdown@plant.mit.edu
Date: Thu, 21 Dec 2000 15:03:35 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: kcn@mit.edu; mwhelan@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: D-Zone; shutdown@plant.mit.edu
> Subject: Shutdown request for building W13 on 12/26
>
>
The following shutdown request is for building W13 on 12/26. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
2-1599
> Status: Normal
> Building: W13 Bexely Hall
> Date: 12/26/00
> Day: Tuesday
> Time: 7 am - 3 pm
> System: Electrical
> Duration: 8 hours
> Reason:
> Relocate heat detectors and tie ins.
>
> Effect:
> There will be a loss of fire alarms during this time.
>
>