Shutdown request for building 13 on 12/26
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Dec 21 13:40:27 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451D2B689@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: andreab@MIT.EDU, B-Zone <B-Zone@MIT.EDU>,
Cust-Coach
<cust-coach@MIT.EDU>, mcoleman@MIT.EDU, rhasselt@MIT.EDU,
schedule@MIT.EDU, src@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 21 Dec 2000 13:40:19 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: andreab@mit.edu; B-Zone; Cust-Coach; mcoleman@mit.edu;
> rhasselt@mit.edu; schedule@mit.edu; src@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 13 on 12/26
>
>
The following shutdown request is for building 13 on 12/26. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
2-1599
> Status: Critical
> Building: 13 1st floor West side emlab and loading dock
> Date: 12/26/00
> Day: Tuesday
> Time: 6 am - 1 pm
> System: Hot water system
> Duration: 7 hour
> Reason:
> Disconnect and remove existing reheat coils. No shutoff valves on the
> return lines.
>
> Effect:
> There will be no heating hot water.
>
>