[53211] in Hotline Meeting
Shutdown request for building 54 on 12/27
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Dec 20 14:58:41 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451D2B5CC@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, kvkeefe@MIT.Edu,
politano@MIT.Edu, schedule@MIT.Edu, sdl-adm-lib@MIT.Edu,
w1mx-officers@MIT.Edu, wendell@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Wed, 20 Dec 2000 14:58:14 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; Cust-Coach; kvkeefe@mit.edu; politano@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; w1mx-officers@mit.edu;
> wendell@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 54 on 12/27
>
>
The following shutdown request for building 54 is for 12/27. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
2-1599
> Status: Normal
> Building: 54
> Date: 12/27/00
> Day: Wednesday
> Time: 7 am - 3 pm
> System: Domestic Hot Water
> Duration: 8 hours
> Reason:
> Broken wedge on 5th floor.
>
> Effect:
> There will be a loss of domestic hot water during this time.
>
>