Emergency shutdown request for building W31 on 12/16

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Dec 15 09:30:21 2000

Message-ID: <82F0D564C5ADD31180EF00508B556451C54C9F@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: bwc@mit.edu, bwiget@mit.edu, D-Zone <D-Zone@mit.edu>, djmartin@mit.edu,
        kenstone@mit.edu, marionoc@mit.edu, pbarratta@mit.edu, slett@mit.edu,
        wheaton@mit.edu, schedule@mit.edu, shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 15 Dec 2000 09:30:16 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	bwc@mit.edu; bwiget@mit.edu; D-Zone; djmartin@mit.edu;
> kenstone@mit.edu; marionoc@mit.edu; pbarratta@mit.edu; slett@mit.edu;
> wheaton@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Emergency shutdown request for building W31 on 12/16
> 
> 
The following emrgency shutdown for building W31 on 12/16.  Please let me
know if this does or does not meet with your approval.

Thnak you
Dawn Simonelli
2-1599

> Status: Emergency
> Building: W31
> Date: 12/16/00
> Day: Saturday
> Time: 7 am - 1 pm
> System: Steam, domestic water, and heat
> Duration: 6 hours
> Reason: 
> Replace repair relief valve on meduim pressure steam station.
> 
> Effect: 
> There will be a loss of hot domestic and heating water, supply heating,
> high medium and low pressure steam and condensate return.
> 
> 