Building 7 shutdown request for 12/20

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Dec 15 08:23:55 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451C54C7F@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.EDU>, blose@MIT.EDU, depopolo@MIT.EDU, jbnorman@MIT.EDU,
        mdhinkle@MIT.EDU, slester@MIT.EDU, schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 15 Dec 2000 08:23:39 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	C-Zone; blose@mit.edu; depopolo@mit.edu; jbnorman@mit.edu;
> mdhinkle@mit.edu; slester@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Building 7 shutdown request for 12/20
> 
> 
The following shutdown request is for building 7 on 12/20.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli

> Status: Normal
> Building: 7
> Date: 12/20/00
> Day: Wednesday
> Time: 7 am - 9 am
> System: Sprinkler System
> Duration: 1/2 hour - 2 hours
> Reason: 
> Tie into existing system piping.
> 
> Effect: 
> There will be a loss of fire protection water during this time.
> 
> 