Bldg. 26 -104,106, 111, 112, 410, 502 and 506 - 11/8 - Reschedule
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 6 13:35:33 2000
Message-ID: <82F0D564C5ADD31180EF00508B5564511055B5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andreab@mit.edu'" <andreab@mit.edu>,
"'b-zone@mit.edu'"
<b-zone@mit.edu>,
"'cust-coach@mit.edu'" <cust-coach@mit.edu>,
"'dudley@mit.edu'" <dudley@mit.edu>,
"'gfp170@rle.mit.edu'"
<gfp170@rle.mit.edu>,
"'kates@mit.edu'" <kates@mit.edu>,
"'ljtrudel@mit.edu'" <ljtrudel@mit.edu>, "'lsc@mit.edu'" <lsc@mit.edu>,
"'mhankin@mit.edu'" <mhankin@mit.edu>,
"'nsteele@mit.edu'"
<nsteele@mit.edu>,
"'radams@mit.edu'" <radams@mit.edu>,
"'safety@mit.edu'" <safety@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'elsye@mit.edu'" <elsye@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 6 Nov 2000 13:32:01 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: andreab@mit.edu; b-zone@mit.edu; cust-coach@mit.edu; dudley@mit.edu;
> gfp170@rle.mit.edu; kates@mit.edu; ljtrudel@mit.edu; lsc@mit.edu;
> mhankin@mit.edu; nsteele@mit.edu; radams@mit.edu; safety@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu; elsye@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 26 -104,106, 111, 112, 410, 502 and 506 - 11/8 -
> Rescheduled Critical Shutdown Request
>
>
The following rescheduled Critical shutdown request for Bldg. 26- 104,106,
111, 112, 410, 502 and 506 on Tuesday, 11/7 is again for your review and
comment. Would you please be good enough to let me know if this new date
meets with your approval.
Thank you again for your time.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 26 104,106, 111, 112, 410, 502 and 506
> Date: 11/7/00
> Day: Tuesday
> Time: 7 AM 3 - 5 PM
> System: Hot and cold domestic and lab process water; lab waste and
> sanitary drainage
> Duration: 8-10 hours
> Reason:
> To re-pipe sewage discharge from this ara of building to manhole structure
> in yard area.
>
> Effect:
> Loss of hot and cold domestic water in 104 (kitchen), 111(Ladies room),
> 112(Men's room), 106 (Janitor's Closet), 410 (Kitchen), Labs 502 and 506
> (also loss of hot and cold lab process water in these labs). Neither
> Emergency showers and eyewashes in the labs nor will lab waste and
> sanitary drainage be operational during this 8-10 hour shutdown period.
>
>