[52455] in Hotline Meeting
Bldgs. 9, 17 and 33 - 10/21 - Domestic Cold Waer Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 18 13:47:19 2000
Message-ID: <82F0D564C5ADD31180EF00508B5564511054DD@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'c-zone@mit.edu'" <c-zone@MIT.Edu>,
"'cust-coach@mit.edu'"
<cust-coach@MIT.Edu>,
"'deedc@mit.edu'" <deedc@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'jobrien@mit.edu'"
<jobrien@MIT.Edu>,
"'mlavalle@mitvma.mit.edu'" <mlavalle@mitvma.mit.edu>,
"'ndk@mit.edu'" <ndk@MIT.Edu>, "'randy@mit.edu'" <randy@MIT.Edu>,
"'sexton@mit.edu'" <sexton@MIT.Edu>,
"'westlund@mit.edu'"
<westlund@MIT.Edu>,
"'edorsch@mit.edu'" <edorsch@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@MIT.Edu>,
"'src@mit.edu'" <src@MIT.Edu>, "'dickp@mit.edu'"
<dickp@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 18 Oct 2000 13:44:18 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: c-zone@mit.edu; cust-coach@mit.edu; deedc@mit.edu; gallant@mit.edu;
> jobrien@mit.edu; mlavalle@mitvma.mit.edu; ndk@mit.edu; randy@mit.edu;
> sexton@mit.edu; westlund@mit.edu; edorsch@mit.edu; shutdowns@mit.edu;
> sdl-adm-lib@mit.edu; src@mit.edu; dickp@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 9, 17 and 33 - 10/21 - Domestic Cold Waer Shutdown
> Request
>
>
The following domestic cold water shutdown request for Buildings 9, 17 and
33 on Saturday, 10/21 is for your review and comment. Would you please let
me know whether this does or does not meet with your approval.
Thank you.
Andrea Nicholss
Operations Center
8-7872
> Status: Normal
> Building: 9, 17 and 33
> Date: 10/21/00
> Day: Saturday
> Time: 7 AM - 11 AM
> System: Domestic Cold Water
> Duration: 4 hours
> Reason:
> Rotate valve at building 33 entrance (in new Mech. Room.)
>
> Effect:
> Loss of domestic cold water in buildings 9, 17 and 33. This means that no
> toilets, bathroom, kitchen sink faucets will be operational during the
> shutdown period.
>
>