[52454] in Hotline Meeting
Bldg. E25 - Animal Quarters - 10/24 - Emergency Panel DPLEIABA Sh
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 18 11:34:36 2000
Message-ID: <82F0D564C5ADD31180EF00508B5564511054DA@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jmganno@mit.edu'" <jmganno@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
E-Zone
<E-Zone@mit.edu>
Date: Wed, 18 Oct 2000 11:31:37 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: jmganno@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; E-Zone
> Subject: Bldg. E25 - Animal Quarters - 10/24 - Emergency Panel
> DPLEIABA Shutdown Request
>
>
The following shutdown request for Bldg. E25 - Animal Quarters - Eemrgency
Panel DPLEIABA on Tuesday, 10/24 is for your review and comment. Would you
please let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E25 - Animal Quarters
> Date: 10/24/00
> Day: Monday
> Time: 7:30 AM - 8:30 AM
> System: Emergency Panel DPLEIABA
> Duration: 1 hour
> Reason:
> Installation of new 60 amp breaker.
>
> Effect:
> Loss of emergency power, supply ventilation and exhaust laboratory air in
> E25 - Animal Quarters during the 1-hour shutdown period.
>
>