Bldgs. W20, W16, W23, W31, W37, W33 and W34 - 8/8-9 - Shutdown Re
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 7 09:34:29 2000
Message-Id: <82F0D564C5ADD31180EF00508B55645110515A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cperry@mit.edu'"
<cperry@MIT.EDU>,
"'pbaratta@mit.edu'" <pbaratta@MIT.EDU>,
"'capone@mit.edu'" <capone@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
"'eisen@mit.edu'" <eisen@MIT.EDU>, "'flett@mit.edu'" <flett@MIT.EDU>,
"'lsc@mit.edu'" <lsc@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
"'pwalsh@mit.edu'" <pwalsh@MIT.EDU>,
"'sdimond@mit.edu'"
<sdimond@MIT.EDU>,
"'dwp@mitvma.mit.edu'" <dwp@mitvma.mit.edu>,
"'graham@mit.edu'" <graham@MIT.EDU>,
"'mdimauro@mit.edu'"
<mdimauro@MIT.EDU>,
"'mkatz@mit.edu'" <mkatz@MIT.EDU>, "'mwf@mit.edu'"
<mwf@MIT.EDU>,
"'djmartin@mit.edu'" <djmartin@MIT.EDU>,
"'jaheiney@mit.edu'" <jaheiney@MIT.EDU>,
"'slett@mit.edu'"
<slett@MIT.EDU>,
"'kenstone@mit.edu'" <kenstone@MIT.EDU>,
"'marionoc@mit.edu'" <marionoc@MIT.EDU>,
"'pbarratta@mit.edu'"
<pbarratta@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'wheaton@mit.edu'" <wheaton@MIT.EDU>,
"'clroyer@mit.edu'"
<clroyer@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 7 Aug 2000 09:33:10 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: dcarlson@mit.edu; cperry@mit.edu; pbaratta@mit.edu; capone@mit.edu;
> D-Zone; eisen@mit.edu; flett@mit.edu; lsc@mit.edu; mwf@mit.edu;
> pwalsh@mit.edu; sdimond@mit.edu; dwp@mitvma.mit.edu; graham@mit.edu;
> mdimauro@mit.edu; mkatz@mit.edu; mwf@mit.edu; djmartin@mit.edu;
> jaheiney@mit.edu; slett@mit.edu; kenstone@mit.edu; marionoc@mit.edu;
> pbarratta@mit.edu; shutdowns@mit.edu; wheaton@mit.edu; clroyer@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. W20, W16, W23, W31, W37, W33 and W34 - 8/8-9 -
> Shutdown RequestThe foll
>
>
The following shutdown request for the above-listed buildings on Tuesday PM,
8/9 to Wednesday AM, 8/9 is for your review and comment. Would you please
let me know whether this does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
3-3257
> Status: Normal
> Building: W20, W16, W23, W31, W37, W33 and W34
> Date: 8/8/09
> Day: Tuesday
> Time: 8 PM (8/8) - 4 AM (8/9)
> System: High, medium, low pressure steam/heating hot water
> Duration: 8 hours
> Reason:
> Repair expansion joint gasket.
>
>
> Effect:
> Loss of high, medium, low pressure steam (heating hot water for buildings
> and as well as hot domestic water (dishwashers, showers, bathroom and
> kitchen faucets) during the shutdown period.
>
>